0006 — Vertical (tracer-bullet) implementation

0006 — Vertical (tracer-bullet) implementation

Section titled “0006 — Vertical (tracer-bullet) implementation”

Status: accepted; phase order superseded by ADR-0009 Date: 2026-04-30 Related: ADR-0001 (multi-repo), ADR-0004 (migrator)

plan/00 wrote Phase 1 in horizontal order: 1.1 migrator → 1.2 helm → 1.3 first migration → 1.13 round-trip test. That order made sense for a single repo, but multi-repo + schema-per-service made each service a vertical slice in its own right.

Vertical implementation: finish a service end-to-end (migrator + schema + Helm + CI + smoke) before starting the next. Phase 1.0 (sdk + proto + infra) is the parallel prerequisite.

The original phase order in this ADR (identity → billing → agents → platform) is superseded by ADR-0009, which keeps the vertical philosophy but starts with agents instead of identity to put a demoable product in front first.

  • Horizontal (plan/00 default). End-to-end verification slips to the end of Phase 1; risk discovery is delayed; the SDK feedback loop is loose; multi-repo dev loses its rhythm.
  • Hybrid (Phase 1.0 horizontal + Phase 1.1+ vertical). In practice identical to vertical because Phase 1.0 is small.

Gain (vertical philosophy, retained):

  • A tracer bullet validates end-to-end at the close of the first service (CI, GHCR, Helm hook, GOPRIVATE, buf codegen — every infrastructure landmine surfaces early).
  • Pattern discovery in service N → straight copy for services N+1..M (2-3× faster).
  • Tight SDK feedback loop: v0.1.0 → v0.2.0 evolves with each service’s learnings.
  • High value of stopping mid-Phase: the first service is production-ready on its own.
  • Mental load is one domain at a time.

Risk:

  • Pattern repetition 4× — drift handled by paper-board/service-template (Phase 5).
  • plan/00 numbering is invalidated. The new plan file is canonical.

Phase 1 estimate (solo dev, full-time): 2-3 weeks for the first service, 3-7 days for each subsequent service. See ADR-0009 + the active roadmap for the concrete order.